The City is pleased to announce an updated timeline for the reconstruction of Stone and Newsome Streets. After discussions with the contractor, the following revised schedule has been confirmed for the upcoming street work:
Revised Construction Schedule:
Pulverization:
Newsome Street: August 14, 2024
Stone Street: August 15, 2024
Cement Stabilization:
Newsome Street: August 21, 2024
Stone Street: August 22, 2024
Asphalt Paving:
Newsome Street: August 26, 2024
Stone Street: August 27, 2024
This schedule allows for a minimum of 72 hours of curing time for the cement before paving begins, ensuring a durable and long-lasting street surface.
We understand the importance of these improvements and appreciate the community's patience as we work to enhance our city's infrastructure.
For more information and updates, please visit our website at www.mineola.com or contact Kyle McCoy at 903-569-6183 or info@mineola.com.