The City is pleased to announce an updated timeline for the reconstruction of Stone and Newsome Streets. After discussions with the contractor, the following revised schedule has been confirmed for the upcoming street work:

Revised Construction Schedule:

  • Pulverization:

    • Newsome Street: August 14, 2024

    • Stone Street: August 15, 2024

  • Cement Stabilization:

    • Newsome Street: August 21, 2024

    • Stone Street: August 22, 2024

  • Asphalt Paving:

    • Newsome Street: August 26, 2024

    • Stone Street: August 27, 2024

This schedule allows for a minimum of 72 hours of curing time for the cement before paving begins, ensuring a durable and long-lasting street surface.

We understand the importance of these improvements and appreciate the community's patience as we work to enhance our city's infrastructure.